The PS206Q project is located in Rego Park, New York, and consists of a 45,000 SF New Construction to the existing
elementary school. New York City School Construction Authority is providing the construction management, while
the design is lead by CTA Architects. In this sizable project, the team is installing concrete on deck, structural steel
superstructure supported by caisson piles, brick and block exterior envelope, aluminum windows and storefronts,
new elevators and new HVAC systems with three new AHUs. Additionally, new gas, electric, sewer and water services
are being installed. Fire protection systems, fire alarms and an intrusion alarm will also be installed and
commissioned. The project follows the NYC Green Schools Guide and Rating System and will achieve compliance
with the Local Law 86 of 2005. The construction is scheduled to be completed in 2022 and is in compliance with ADA
requirements including ramps, lifts and elevators.
Project Details
Owner:
New York City School Construction Authority
Architect:
CTA Architects P.C.
Location:
Queens, New York
Completion:
2022